Kesko automates new logistics center with Knapp
The grocery retailer is responding to changed requirements for its logistics. Faster deliveries and a broader range of products increase the demands on the provision of goods. Therefore, the new infrastructure should also be able to accommodate increasing order volumes and future requirements.
Multi-year Preparation of the Project
The decision for Knapp was preceded by a multi-year preparation phase. Both companies have been working together for a long time. In the planning process, a technology platform was developed that is intended to handle different types of customers and orders.
According to company information, the selection of the project partner was influenced by the available technology portfolio, research and development competence, and the scalability of the system. The logistics infrastructure is thereby intended to adapt to changing requirements and growing order volumes over the long term.
Automated Pallet Handling with High-Bay Warehouse
The planned overall system connects automated and manual warehousing processes. An automated process with a high-bay warehouse is intended for pallet handling.
For smaller containers and individual items, Kesko plans a shuttle-based small parts storage. The items are provided in sequence from the "Evo Shuttle" and picked at ergonomically designed goods-to-person workstations.
Automation step-by-step operational from 2029
With the combination of different storage and picking technologies, the facility is intended to cover various order processing requirements. At the same time, the system is designed for future adjustments and increasing order volumes.
Following the installation planned for 2028, Kesko aims to put the new automation into operation in two stages. The step-by-step commissioning is scheduled for the years 2029 and 2030.